Blue Mountain Christian University reports progress on Center for Grace & Healing construction

Construction at Blue Mountain Christian University’s Center for Grace & Healing has entered its 36th week, with several key activities underway, according to a university update.

Structural steel erection continued on site this week, along with overhead MEP (mechanical, electrical, and plumbing) rough-in work on the lower level. Fire suppression system rough-in also progressed on the lower level.

Exterior cold-formed metal framing and interior framing are ongoing. Installation of exterior sheathing has also continued. Rebar and wire mesh for slab-on-deck pours have been installed, with several pours completed this week, including slab-on-grade block-out pours.

The project has also seen the start of exterior waterproofing and foundation retaining wall backfilling, marking further milestones in the construction process, according to university officials.

Source: Original Article

Jon Ross Myers

Jon Ross Myers is the executive editor and publisher of the Mississippi News Network, Mississippi's largest digital only media company. He can be reached at editor@tippahnews.com

Leave a Reply

Your email address will not be published. Required fields are marked *