Blue Mountain Christian University said work continued this week on the Center for Grace & Healing, bringing the project closer to completion.

Inside, the university said crews installed lab casework and millwork, painted lobby ceilings, completed interior storefront glazing and worked on doors, handrails and other interior finishes. The university said crews also prepared the space for lecture hall seating.

Outside, the university said crews worked on site masonry, grading, hardscapes, exterior lighting and an Americans with Disabilities Act ramp. Workers also installed flashing for the rooftop patio, the university said.

The university said each week’s work brings the project another step closer to completion.